MOD Considers Naval Workload Crisis
23 August 2004
In response to pleas by senior shipbuilding
industry executives for a change in Ministry of Defence warship procurement
plans, the Secretary of State for Defence, Mr Geoffrey Hoon, has ordered an urgent
investigation.
The investigation is being
led David Gould, Deputy Chief Executive of the Ministry of Defence’s (MOD’s)
Defence Procurement Agency (DPA) and Rear-Admiral Ric Cheadle, the DPA’s
Director of Land and Maritime programmes. It is considering warnings that a lack of long-term coherency in the
MOD's equipment programme is threatening the UK's naval industrial base, with the objective of
developing a comprehensive strategy for naval shipbuilding. The work is being
carried out by the MOD and DPA, with the participation of the Department of
Trade and Industry (DTI) and other interested government agencies.
|

RFA Lyme Bay (Swan Hunter)
|
A key input will be a
recently completed report by the Rand Corporation, the MOD engaged Rand in late
2003 to consider whether the UK has enough naval shipbuilding capacity to
undertake work in parallel on programmes such as Type 45 destroyer and the
Future Aircraft Carrier (CVF) and to meet demanding in-service dates, and the
impact of other programmes such as Military Afloat Reach and Sustainability
(MARS) which may require new skills to meet commercial and legal standards not
seen before in military vessels. The
Rand Corporation report also compares available skills and capacity with that
which will be required.
Rand
Corporation had predicted in a revision of its earlier 2001 report for the MOD
("The Royal Navy's New-Generation
Type-45 Destroyer: Acquisition Options and Implications") that:
“Demand for bluecollar workers doing direct labour declines slightly between
now and 2006, after which demand increases rapidly to a peak of nearly 7,000
direct workers in 2010—almost double the level in 2005. Clearly, the main risk for the MOD’s future
programmes is maintaining and expanding the labour force in the next several
years while managing a small dip in demand.”
| Table 1: MOD Naval Orders - By shipyard
at given dates |
| Shipyard(s) |
August 2002
|
August 2004 |
August 2006
(Current plans) |
Comments |
|
Appledore Shipbuilders, Devon
|
Survey Ships |
None |
None |
In to receivership 30 September 2003. Now
owned by DML |
|
BAE Systems Naval Ships, Govan and Scotstoun
|
Auxiliary Oiler,
LSD(A)s
|
LSD(A)s,
Type 45 destroyers
|
Type 45 destroyers |
|
|
BAE Systems Submarines Business, Barrow-in-Furness
|
Auxiliary Oiler,
LPD(R)s,
Astute submarines |
Astute submarines |
Astute submarines |
Ceased surface ship construction May 2004
|
| Swan Hunter, Tyneside |
LSD(A)’s |
LSD(A)s |
None |
|
| Harland & Wolff Holdings plc, Belfast |
RoRo’s |
N/A |
N/A |
Ceased shipbuilding March 2003 |
| Vosper Thornycroft (UK) Ltd, Woolston |
Future OPV’s |
N/A |
N/A |
Yard closed March 2004 |
|
VT Shipbuilding, Portsmouth
|
N/A |
Type 45 destroyers |
Type 45 destroyers |
Yard opened September 2003 |
In
fact the slump in shipyard workload is proving to be much longer and deeper
than Rand had forecast. Since that report was written Harland & Wolff has withdrawn from
shipbuilding, Appledore Shipbuilders has gone in to receivership with the loss
of up to 550 jobs, and BAE Systems has announced at its Barrow-in-Furness shipyard alone about 1300 redundancies, reducing the
total workforce there to about 2,500.
| Table 2: MOD Naval Equipment
Acquisition Projects - Recently completed or soon to be completed |
|
Ship Class
|
Builder(s) |
Displacement, FL (tonnes) |
No. Built |
In Service Date (Last of Class) [1] |
Project Cost |
|
Duke Class - Type 23 frigate
|
BAE Systems Marine, Scotstoun [2] |
4,300 |
16 |
2001 |
? (About £190 million each for late build units) |
|
Sandown Class - Single Role Minehunter
|
Vosper Thornycroft, Woolston |
450 (standard) |
12 |
2001 |
? (About £40 million
each for late build units) |
|
Albion Class - Landing
Platform Dock (Replacement)
|
BAE Systems Marine, Barrow |
16,981 |
2 |
2005
[3] |
£790 million |
|
Point Class - RoRo
|
Harland & Wolff, Belfast |
20,000 |
2 + 4 [4] |
2003 |
£80 million (for 2 H&W ships only) |
|
Wave Class - Auxiliary Oiler
|
BAE Systems Marine
|
31,500
(12,500 light) |
2 |
2003 |
£211 million |
|
Echo Class Survey Ships
|
Appledore Shipbuilders, Devon
|
3,500 |
2 |
2003 |
£130 million |
|
River Class - Future OPV
|
Vosper Thornycroft, Woolston
|
1,677 |
3 |
2003 |
£60 million (lease arrangement) |
|
Bay Class - Landing Ship Dock (Auxiliary)
|
Swan Hunter, Tyneside; BAE Naval Ships,
Govan
|
16,160 |
4
|
2006 |
£320 million [5] |
|
[1] The in-service date may be a considerable
period after the ship was materially completed by the shipyard.
[2]
For all units completed since 1995.
[3] HMS Bulwark, the second and last unit
was delivered to the Royal Navy 12 July 2004.
[4]
Two ships were built by Harland & Wolff, another four were built by
Flensburger Schiffsbau-Gesellschaft in Germany.
[5] Subject to claims for cost
overruns from Swan Hunter and BAE Systems which may increase final cost to
£380 million.
|
The problem is caused by a
prolonged gap in naval ship orders from the MOD. At the start of the new millennium the UK shipbuilding industry had a fairly healthy workload,
consisting mostly of a backlog of MOD orders plus significant export orders for Malaysia and Brunei. But since
then most of these orders have been completed (ref. Tables 2 and 3) while the
failure of the UK warship industry to win any significant export orders since
the 1990’s has not helped, making the industry even more dependent upon the MOD
for its survival. However the MOD itself
has not placed any new orders since 2001, delays to large projects and a
simultaneous failure to proceed with smaller project due to a lack of budget
means that when the last of the LSD(A)’s completes in early 2006, the only MOD
work (indeed almost the only work) in UK shipyards will be the SSN HMS Astute
and the first Type 45
destroyers HMS Daring, HMS Dauntless (work due to start August
2004) and HMS Diamond (work due to
start Spring 2005). Industry has been
dismayed by the multi-year slippage of programmes such as CVF, the Astute
Second Buy and Joint Casualty Treatment Ship (JCTS), which it had hoped would
now be entering the Demonstration and Manufacture (D&M) Phase, with
fabrication work already started or soon to start. The MOD also dismissed an unsolicited but
aggressively priced proposal made by BAE Systems in 2002 to order two
additional Wave Class Auxiliary Oilers in advance of MARS in order to fill the
work gap in its shipyards. Currently the
MOD does not expect to sign any significant new contracts prior to late 2005 at
best, and it will be 2007 or 2008 before shipyards will be able to cut steel on
major projects such as CVF and MARS. The
result is a desperate shortage of work in UK shipyards and large scale layoff’s, in April 2004 the
Chairman and owner of Swan Hunter, Mr Jaap Kroese, warned: "The reality is
that everybody [1500 workers] will be made redundant and the yard will be
mothballed for two years."
| Table 3: MOD Naval Equipment
Acquisition Projects – Future Projection |
|
Ship Class
|
Builder(s)
|
Displacement,
Full Load (tonnes) |
Number Planned |
Planned
Main Gate Year , actual or (planned)
|
Number ordered by 1 August 2004 |
Target In-Service Date (First of Class) [1] |
Estimated Project Budget |
|
Daring Class Type 45 Destroyer
|
BAE Naval Ships, Govan and Scotstoun; VT Group, Portsmouth
|
7,350 |
8
|
2001
|
6
|
2007 [2] |
£5,546 million
(first 6 units only)
|
|
Astute Class SSN
|
BAE Systems Submarines, Barrow
|
6,500 (surface)
|
5 or 6 [3]
|
1997
|
1+2
[4]
|
2009 |
£3,710 million billion (first 3 units only) |
|
Future Aircraft Carrier (CVF)
|
Probably BAE Naval Ships; Swan Hunter,
Tyneside; VT Shipbuilding, Portsmouth; Babcock DES,
Rosyth
|
About 60,000
|
2
|
(2005)
|
0
|
2012
[2] |
Approx £3.2 billion [5] |
|
Military Afloat Reach & Sustainability (MARS)
|
?
|
Up to 40,000
|
8-12
|
(2006)
[7]
|
0 |
2010
[7] |
Approx £2 billion |
|
OPV(H)
(Castle Class Replacement)
|
Probably VT Group or DML Appledore |
1,500-2,000
|
1-2
|
(2004)
or (2009)
|
0 |
2006 or 2011 [6] |
£50 million (lease arrangement) |
|
OMAR (RFA Diligence Replacement)
|
?
|
?
|
1
|
?
|
0
|
2006
|
? |
|
Joint Casualty Treatment Ship (JCTS)
|
?
|
?
|
1
|
(2007)
|
0
|
2008
|
£30 million |
|
Future Surface Combatant (FSC)
|
?
|
?
|
Up to 16
|
(2008)
[7]
|
0
|
2015
[7]
|
? |
|
[1]
The in-service date may be a considerable period after the ship was
materially completed by the shipyard, e.g. perhaps 18 months in the case of
the first T45 destroyer.
[2]
One or two year slippage expected.
[3]
Five or six officially planned, but up to eight may eventually be ordered
including replacements for the three “Final Update” Trafalgar Class.
[4]
Three submarines were ordered in 1997, but work on two was effectively
suspended in February 2003 pending progress on the lead unit (HMS Astute) and
contract renegotiation.
[5]
Assessment Phase £143 million, Demonstration and Manufacture Phase “most
likely” £3,057 million. There is
considerable upwards pressure on these costs.
[6] The MOD is considering
advancing the ISD to 2006 if a proposed leasing arrangement is financially
attractive.
[7] May be delayed, Initial Gate was planned for
Spring/Summer 2004 but not occur.
|
But
pervasively, by the end of the decade those UK shipyards able to build large
ships will be struggling to cope with an excess of MOD work as multiple
projects simultaneously reach the manufacture stage (ref. Table 3) – a
"famine to feast" situation, and a driver behind VT Group’s decision
to close its old and restricted capacity Woolston shipyard and open a modern
new facility at Portsmouth Naval Base that is more suited to the MOD’s
anticipated future requirements. As the
MOD is already warning industry that it will expect planned in-service dates
for programmes such as CVF to be met despite the delay in placing orders,
unless the shipbuilding industry can regenerate its workforce and construction
capacity with improbable speed from 2008, problems and slippages seem to be
inevitable.

Chart 1: MOD Naval Equipment Programmes from 2000 to 2018.
Schedules are illustrative only.
The anticipated problems
could be solved by reconsidering the rate at which the MOD’s required
capabilities are delivered - effectively bringing forward contracts in order to
fill the gap. But while adjusting and
advancing MOD orders in order to provide shipyards with a more evenly spread
workload may be the sensible approach, the options available are actually very
limited given the MOD’s tight budget situation with little financial
flexibility, the disruptive effect of major changes on a carefully an equipment
plan that looks ten years ahead, and the long lead times associated with many
ideas. For example, calls to advance the
building of the planned new aircraft carriers are considered to be simply not
realistic as the CVF project just won’t be ready to move on to the D&M
Phase for another year.
However the MOD, DPA, DTI and
shipyards are now working together, are assessing the capabilities of British
yards, and are holding monthly meetings to try to tackle the identified
problems. A spokesman for the DPA said
"Talks have been taking place regarding this matter. They remain on-going, and are continuing to
take place between all interested parties."
Possible recommendations of
the Gould Committee include:
-
Subsidising
shipyards and major suppliers to retain a core of key and experienced workers. The
MOD may have already taken this approach with Rolls-Royce in to relation to nuclear
submarine propulsion systems.
-
Ordering a fourth
Astute Class nuclear submarine in order to help sustain the supplier base.
-
Rapidly ordering
one or two Castle Class OPV replacements, with a mid-2006 ISD. VT Shipbuilding and DML Appledore are
competing for the OPV(H) order.
-
Finally ordering
the long planned Joint Casualty Treatment Ship (JCTS), a project repeatedly
delayed due to lack of funding.
-
Advancing the
in-service date of the MARS project.
-
Expediting other
capabilities such as a proposed Forward Aviation Support Ship (ASS).
Alternatively
the Committee may decide, or have to decide due to funding constraints, to take
no action and let events take their due course - at least in the near term. If necessary, several options could be pursued
a later date. For example, the inward
investment of skills and resources into UK shipyards from overseas could be encouraged; and the
government might not be adverse to some UK shipyards being incorporated in to a pan-European
company along the model of EADS in the aerospace sector.
Another
option is that government’s current industrial policy requiring RN warships and
new construction RFA auxiliaries to be wholly built in the UK could be relaxed. Indeed one respected analyst and advisor to the MOD Professor Keith
Hartley of the University of York in his 2003 paper "Naval Shipbuilding in the UK and Europe: A Case for Industrial
Consolidation?" said “Warship building is a classic example of
European governments failing to exploit the gains from competition and free
trade. … some nations such as the UK are committed to national procurement of warships …
but the commitment to ‘buy British’ means that foreign firms which might be
lower-cost suppliers are not able to bid for UK warship contracts. Extending the Single Market to warships and other defence equipment
procurement would offer gains to taxpayers and the Armed Forces; but the losers
from such a policy would be the inefficient.”
Critics of the current ‘buy
British’ policy argue that the UK still has a successful aerospace industry despite
long importing aircraft and missiles, including Trident missiles for its
nuclear deterrent from the USA. They can also
point out that the hull construction, assembly and outfitting of a modern
warship makes up typically only about one third of the total “system
cost”. The “British built” Type 45
destroyers will have about a 50% UK content by value, with everything from
steel, to weapons systems to the bridge controls being imported, and BAE
Systems and Thales Naval won’t promise any better for CVF. Bidding contractors and shipyards in France, Poland, Germany and the Netherlands which have in the past have run foul of MOD’s “buy
British” requirement are now scenting real opportunities to build abroad
modules or even whole ships for the MOD in the future.
It
is expected that the MOD will make an announcement later this year on its
conclusions. Those conclusions are
likely to have a profound effect upon the size and capabilities of the future UK shipbuilding industry.