![]() |
![]() |
![]() |
|
|
This section documents progress on the Future Aircraft Carrier (CVF) Programme via official statements. Statements are given in date order. Source: Select
Committee on Defence, Session 2004-2005,
Defence -
Fourth Report - Defence Procurement Further memorandum by the Ministry of Defence [Info dated February 2005] FUTURE CARRIERS—CVF PROGRESS ON CVF PROGRAMME
Source: Hansard,
Written Ministerial Statements DEFENCEFuture Aircraft CarrierThe Secretary of State for Defence (Mr. Geoffrey Hoon): I am pleased to announce that we have decided to extend the future aircraft carrier (CVF) programme assessment phase. This extension will enable us to carry out further risk reduction work and increase the maturity of the design prior to making our main investment decision on demonstration and manufacture (D&M). In line with smart acquisition principles by spending the right amount of time and money in the assessment phase, we will gain a better understanding of the technical and supply-side risks before we make any major commitments. We had planned to complete this risk reduction work within the original demonstration phase. The underlying programme has not been adjusted, but rather the point at which we make the main investment decision has shifted. We anticipate moving into the D&M phase during 2005, following the main gate decision. At this point we intend to finalise performance, time and cost parameters of the carriers. These will continue to be refined during the remainder of the assessment phase. Our target in service dates (ISO) for the CVF remain 2012 and 2015. When built the two vessels will be the largest and most powerful warships ever constructed in the United Kingdom. We have also agreed the alliancing principles with industry for the CVF programme which confirms the commitment of all parties to the programme and to an alliance based on commercial best practice. The alliancing principles will provide the most effective way of managing risk and reward and will bring together all parties with a vested financial interest, thus ensuring that we deliver CVF collaboratively. We will now discuss and agree the detailed alliancing arrangements with industry, including the roles and responsibilities of alliance members. Source: Select
Committee on Defence, Session 2003-2004,
Defence - Sixth Report - Defence Procurement Further memorandum by the Ministry of Defence [Info dated April 2004] 15. FUTURE CARRIERS (CVF) PROJECT SUMMARY 1. Under the CVF
project, we will procure two large
aircraft carriers to
replace the three Invincible-class
carriers from around 2012. These
carriers will operate the
Short Take Off and Vertical Landing (STOVL) variant of the Joint Strike
Fighter (which has been selected to fill the role of Joint Combat
Aircraft), the Maritime
Airborne Surveillance and Control (MASC) capability and other
aircraft in a variety of
roles. 2. CVF received Initial
Gate approval in December 1998 and in November 1999, competitive
contracts for the Assessment Phase were awarded to BAE SYSTEMS and
Thales UK. Following the January 2003 announcement of an alliance
approach involving BAE SYSTEMS, Thales UK and the MOD as the best method
for delivering CVF, Stage 3 of
the Assessment Phase formally started on 5 September 2003 and ran until
31 March 2004. Work is continuing to develop the
carrier design to a high
degree of maturity and the MOD is discussing the alliancing strategy for
the Demonstration and Manufacture (D&M) Phases with the two companies.
The programme remains on target to meet the ISDs of 2012 and 2015. POLICY CONTEXT AND CAPABILITY REQUIREMENT 3. The requirement for the Future
Aircraft Carrier (CVF)
was endorsed in the Strategic Defence Review (SDR) which identified a
continuing need for rapidly deployable forces with the reach and
self-sufficiency to act independently of host-nation support. The SDR
concluded that the ability to deploy offensive air power will be central
to future force projection operations, and
aircraft
carriers can provide valuable
flexibility in a range of operational circumstances. The SDR conclusions
were endorsed by the New Chapter work of 2002 and the Defence White
Paper in December 2003. 4. It was therefore decided to replace the three INVINCIBLE-class
carriers with a new class of
two larger and more capable carriers
known as CVF. These
ships—which will be called "Queen Elizabeth and Prince of Wales"—will
have the objective of supporting an increased emphasis on offensive air
operations and force projection as a central component of joint maritime
operations. 5. The design parameters for the ships continue to evolve to meet
our capability requirement; as a routine part of the Assessment Phase,
cost capability trade-off work has been carried out to ensure that the
programme provides the best value for money capability that is
consistent with the needs of defence policy and is affordable within the
overall defence budget. We anticipate being in a position to refine our
assumptions towards the end of the year and in the meantime, our primary
focus remains on delivering the capability that offers the best value
for money solution. COSTS 6. Costs incurred to the end of 31 March 2004 (including
pre-feasibility studies) total around £153 million. This represents an
increase of £35 million over the approved Initial Gate costs of £118
million as a result of the revised procurement strategy and
renegotiations to the Stage 3 contracts that were placed with the two
companies in September 2003. The costs remain within the boundary set
for the project. 7. Estimates for the Demonstration and Manufacture (D&M) are being
prepared on a progressive basis throughout the Assessment Phase. The
current estimate of most likely (50%) cost for the
carriers is around £3 billion
(including combat system but excluding the
aircraft). Cost of Capital
charges add a further £450 million to the estimate. Total acquisition
costs are being refined during the remainder of the Assessment Phase to
take into account maturing design and price information from BAE SYSTEMS
and Thales UK. IN -SERVICE DATE (ISD) AND SERVICE LIFE 8. ISD will be declared when the military capability provided by
CVF is assessed as available
for operational use. The first CVF
is scheduled to enter operational service in 2012 and the second in
2015. Current work in the CVF
Assessment Phase suggests that it is possible to meet these dates,
although work is continuing to identify the optimum design and build
strategy. Each CVF is planned
to have an in-service life of 30 years with a stretch target of up to 50
years. ACQUISITION APPROACH 9. The CVF Assessment
Phase began in November 1999 with the award of competitive contracts to
BAE SYSTEMS and Thales UK and has been split into a number of phases.
Stage 1 involved the examination of several
carrier designs and an
assessment of the costs of extending the lives of the three existing
carriers by 10 years to
provide a baseline against which the cost effectiveness of all the
options could be evaluated. During Stage 2, BAE SYSTEMS and Thales UK
concentrated on refining their designs and taking key trade-off
decisions. From September 2002, work concentrated on building the
carriers to an innovative,
adaptable design which will enable them to operate the STOVL variant of
the JSF aircraft; and with
modifications, a further generation of conventionally launched
aircraft. This represents a
sensible way to secure the best return from our investment in the
carriers and good long term
value for money. 10. An innovative Continuous Assessment process was used
throughout Stage 2 to evaluate the contractors' performance. This
concluded that an alliance approach involving BAE SYSTEMS, Thales UK and
the MOD represented the best approach to delivering
CVF within the time and cost
parameters. The alliance procurement strategy was announced in January
2003. The alliance is envisaged as a co-operative relationship between
the customer (the MOD) and the key contractors which will enable us to
make the most of the resources and strengths of all the alliance members
with the shared objective of improving on agreed performance targets.
11. A third Stage of the Assessment Phase was taken forward on the
basis of an evolving alliance approach and formally started on 5
September 2003. The maturity of the design was increased and discussions
continued to be held with the companies on the alliancing strategy to
take the programme through the D&M Phases. Design maturity has already
reached a comparatively higher level for
CVF than for other legacy
maritime projects. We believe that the alliance approach remains the
best method for delivering the programme to time and cost. Stage 3
completed on 31 March 2004. Advice has been submitted to Ministers on
the way forward for the programme, and an announcement is expected
shortly. 12. Opportunities for international co-operation are being
reviewed during Assessment, especially for equipment systems and
subsystems. Although whole ship collaboration is unlikely to be a viable
option, opportunities to share best practice in assembly integration and
outfitting will be explored. In particular, discussions are continuing
with the French and US to explore areas for possible co-operation in
common areas of aircraft
carrier technology at a system
or sub-system level. There is agreement between the UK and France, at
Ministerial level, that industry to industry co-operation represents the
best way forward for any UK/France co-operation on
aircraft
carrier issues. 13. The CVF programme is
adopting and further developing a range of Smart Acquisition techniques
and has embedded a number of Smart Acquisition processes into its
activities with the Aircraft
Carrier Team (formed by BAE
SYSTEMS and Thales UK). A greater emphasis is being placed on
identifying, evaluating and implementing effective trade-offs between
system performance, whole-life costs and time. Incremental acquisition
is being adopted in areas such as mission systems, which will allow for
the incorporation of up-to-date technologies to avoid obsolescence.
SMART project management processes are being used to achieve early risk
reduction, such as the use of Technology Readiness Levels (TRL) to
ensure that any technologies that need developing have reached a
sufficient TRL at appropriate points within the acquisition cycle. We
are also developing a mature risk assessment process based around a
joint risk register, linked with Earned Value Management (EVM), which
enables the project team to track and manage key risks and ensure that,
if required, appropriate mitigation strategies are being implemented. INDUSTRIAL ISSUES 14. In accordance with current government policy for the
construction of Royal Navy warships, the
CVF will be assembled in UK
shipyards. Industrial factors were taken into account in the decision to
adopt the alliance approach for CVF;
in January 2003, we identified that, subject to value for money
considerations, the best way forward was for
CVF to be potentially built by
a combination of four UK shipyards (BAE SYSTEMS Naval Ships at Govan,
Vosper Thornycroft at Portsmouth, Swan Hunter on Tyneside and Babcock
BES at Rosyth) although the involvement of other UK yards has not been
ruled out. This approach was underpinned by a detailed analysis of
facilities, capabilities and likely capacity across the UK shipbuilding
industrial base. Final decisions will be made based on achieving value
for money while taking due account of the capability, capacity and
resources of UK industry to meet the full range of planned naval
programmes. Discussions are continuing with the yards on the precise
arrangements and work allocation on this basis. The predicted overall
loading in the yards during the CVF
construction timefraname is also being examined. It is estimated that
CVF will sustain or create
some 10,000 jobs across the UK during the course of its design and
manufacture. 15. It is unlikely that this project will lead directly to
whole-ship sales, although the commercial marketing of
CVF design skills and
production technology could benefit UK industry. Much of the ship's
equipment could have export potential. Industrial Participation
proposals will be invited, as appropriate, for offshore content of the
proposed solution. IN -SERVICE SUPPORT 16. Contractor Logistic Support (CLS) will be considered for some
or all of the maintenance and logistics and OLS options for up to 30
years are being examined during Assessment. One option to be considered
is the adoption of best practice in supply chain techniques, to minimise
MOD ownership of spares, by contracting for agreed spares availability
from industry. We are also developing options to let a contract for an
Initial Support Period up to and including the dry docking of the first
vessel. 17. The upkeep cycle of the CVF
will reflect both the vessels' modern design and developments in upkeep
practice such as "reliability centred maintenance" rather than lengthy
and expensive refits. This will enable availability requirements to be
met by only two carriers. NEXT STEPS 18. Stage 3 completed on 31 March 2004. Advice is currently with
Ministers on the way forward for the programme, and an announcement is
expected shortly. In the meantime, work on the project continues and
negotiations are on-going between the MOD and the companies over the
alliance strategy for the Demonstration and Manufacture phases. The
target ISDs for the carriers
remain unchanged at 2012 and 2015. April 2004 Source: Select
Committee on Defence, Session 2002-2003, Defence
- Eighth Report - Defence Procurement Memorandum from the Ministry of Defence (May 2003) FUTURE CARRIERS—CVF Under the CVF project, we will procure two large aircraft carriers to replace the three Invincible-class carriers from around 2012. These carriers will operate the STOVL variant of the Joint Strike Fighter, the Maritime Airborne Surveillance and Control (MASC) capability and other rotary wing aircraft in a variety of roles. Competitive contracts for the CVF Assessment Phase were awarded in November 1999 to BAe Land and Sea Systems (now BAE SYSTEMS) and Thomson-CSF (now Thales Naval Ltd). As was announced on 30 January 2003, we now envisage taking the project through an alliance approach, with BAE SYSTEMS acting as the Prime Contractor and Thales taking a major role as the Key Supplier. The Ministry of Defence will also take up a formal role in the alliance. The MoD is currently negotiating with the two companies on establishing the alliance structure. A move into the next phase of the project is expected in May. Operational Requirement The SDR concluded that the three INVINCIBLE-class
carriers should be replaced with a new class of larger and more capable
carriers, known as the Carrier Vessel Future (CVF) class. The objective
is for these ships to support an increased emphasis on offensive air
operations and force projection as a central component of joint maritime
operations. As such, it is intended that CVF will operate the STOVL
variant of the F35 Joint Strike Fighter (JSF), the Maritime Airborne
Surveillance and Control (MASC) capability and other rotary wing
aircraft from all three services in a variety of roles. The SDR also saw
advantage in future carriers being capable of carrying more fixed-wing
aircraft than the INVINCIBLE class vessels, in order to be able to
contribute more effectively to the support of operations on land and at
sea. Trade-offs Numbers Strategic Defence Review Military Capability Equipment to be Replaced and In-Service Date Acquisition Strategy The first stage of the Assessment Phase involved the examination of carrier design options and helped inform the UK's decision, in January 2001, to select JSF as the aircraft with the best potential to meet the JCA requirement. The remainder of Stage 1 then focused on vessels capable of supporting JSF. This stage of Assessment was completed in June 2001. Stage 2 of the Assessment Phase ran from November 2001 to November 2002, during which time the competing consortia concentrated on refining their designs. For much of this stage, a twin-track approach was followed looking at designs capable of supporting the two variants of JSF under consideration for the JCA role; namely a conventional CV carrier, utilising catapults and arrestor gear, and a STOVL design, fitted with a ramp and optimised for STOVL aircraft operations. When the decision was announced on 30 September 2002 to proceed with the STOVL variant of JSF, it was concluded that, in the interests of flexibility, value for money and maximising our investment over the whole of its service life, the carrier should be built to an innovative adaptable design. This will be CV based but modified to operate STOVL aircraft in the short to medium term whilst retaining the ability to be adapted to operate other aircraft types after the JSF leaves service. During Stage 2, the Department continuously assessed the two consortia's work in order to provide a firm factual basis for the selection of the preferred prime contractor in early 2003. The evidence from the Continuous Assessment process confirmed that, in order for the carriers to enter service on time, both companies would need to augment substantially their available resources to achieve the necessary maturity before manufacturing could begin. Our detailed analysis showed that each company has significant strengths. BAE SYSTEMS displayed a good understanding of the project's complexities in its project management and prime contracting, and had developed a good relationship with all the key shipyards. The company also demonstrated the skills that are necessary to integrate the different systems into an effective warship. Thales UK provided an innovative design that is flexible enough to meet our needs and has strengths in a number of key areas, including weapon and defence systems and the interface between the ship, aircraft and flight deck operations. It was this evidence that led us to the conclusion that, to deliver value for money, provide the best capability and significantly reduce risk to the programme, we needed to exploit all the strengths of both companies. An alliance approach appeared to offer the best means of bringing together the necessary resources and expertise to deliver the programme. We envisage that this alliance will be led by BAE SYSTEMS as the preferred prime contractor, with responsibility for project and shipbuilding management. Thales UK will assume a major role as key supplier to produce design solutions. The Ministry of Defence will also take up a formal role in the alliance. The precise details of the alliance arrangement are now being discussed and agreed between the two companies and the MoD. They will be based on all parties working together, as a single team to deliver the capability to time and cost. The MoD's role will include ensuring the availability of other assets for which we are rightly responsible, such as suitably trained manpower and the JSF aircraft, during the design and build phase. It is anticipated that the alliance will formally start in the third and final stage of assessment in May and that this will take the programme through to the award of a Demonstration and Manufacture (D&M) contract early in 2004. In order to avoid any delays to the programme, both companies are continuing to progress key elements of assessment phase activity ahead of the formal commencement of Alliance working. The Demonstration element of the D&M phase will initially continue design and risk reduction work from the Assessment Phase, the intention being to achieve the highest possible level of design maturity before construction begins. The planned In-Service Dates of the two carriers remain unchanged at 2012 and 2015. Alternative Acquisition Options Co-operation with France and the US Export Potential Industrial Factors Smart Acquisition The alliance proposal for CVF emerged from the findings of the CA process. This has provided a new and faster means of determining the relative strengths and weaknesses of competing contractors. The process also broke new ground by addressing significant but less tangible issues—such as the contractors' ability to work with the MoD, which is important when the MoD could be working with the selected prime and key supplier for many years. The CA process ran throughout Stage 2 and provided the MoD with a robust and transparent method of determining the way ahead for the programme. It was a move away from the traditional tender assessment approach and enabled the MoD to make its decision more quickly than would otherwise have been possible. This innovative alliance approach also builds on the principles of the Defence Industrial Policy document published in October 2002. It will enable us to make the most of the resources and strengths of both companies and the skills and expertise of the IPT. We will continue to maximise the advantages offered by competition (at the sub-contractor level) during the remainder of the Assessment Phase, thus ensuring that we achieve best value for money. The alliance approach is intended to allow a seamless transition from Assessment through to Demonstration and Manufacture and will directly address the concerns of industry and the MoD about the level of risk reduction required on major programmes. Both BAE SYSTEMS and Thales have welcomed the alliance approach. Acquisition Phases Milestones and Costs
In-Service Support Contractor Logistic Support (CLS) will be considered for maintenance and logistics where value for money and coherence with wider Royal Navy support systems can be demonstrated. The benefits of CLS include a strong focus on reliability for initial designs; better standards of availability, reliability, and maintenance; and an incentive to the contractor to design and build systems that minimise support costs. One option to be considered is the adoption of best practice in supply chain techniques, to minimise MoD ownership of spares, by contracting for agreed spares availability from industry. The upkeep cycle of the CVF will reflect the vessels' modern design, and developments in upkeep practice such as "reliability centred maintenance" rather than lengthy and expensive refits. This will enable availability requirements to be met by only two carriers. Front Line Numbers Interoperability Disposal of Equipment Replaced In-Service Life Development Potential Back to TopSource: UK
Ministry of Defence The Secretary of State for Defence, Geoff Hoon MP, set out in the House of Commons on 30 January 2003 a proposal for BAE Systems and Thales UK to work in partnership to design and build two new aircraft carriers for the Royal Navy, planned to enter service in 2012 and 2015. The competition for the future carrier programme's Prime Contract had been closely run between bids from the two companies. Following detailed analysis of their proposals by the MOD, particular strengths were identified in each. The Ministry of Defence has therefore recommended drawing these areas of expertise together to provide the best possible solution for meeting the project's requirements. It has suggested that the partnership would be led by BAE Systems as the Prime Contractor, responsible for project and shipbuilding management, while Thales UK would be the Key Supplier for the whole ship design. The MOD would participate in the Alliance, managing appropriate risks and contingencies, as well as ensuring the provision of necessary assets such as trained manpower and the JSF aircraft which the carriers will embark. Both companies have indicated their willingness in principle to participate in such an Alliance, which would be underpinned by robust contractual agreements. Work will now be carried through to Spring 2004, when the final investment decision for the programme is scheduled. It is currently envisaged that building work for the two carriers would involve four shipyards: BAE Systems at Govan, Vosper Thornycroft at Portsmouth, Swan Hunter on Tyneside and Babcock BES at Roysth. Other shipyards may become involved in due course, while Rolls-Royce is expected to provide the engines. Some 10,000 jobs are likely to be created or sustained by the project. Back to TopSource: UK
Ministry of Defence RAF and Navy To Get Supersonic Jump Jets To Fly From New Carriers The Royal Air Force and Royal Navy are to get a force of
the world's most advanced stealthy supersonic jump jets to equip both
the new class of two large aircraft carriers and to fly from shore
bases, Defence Procurement Minister Lord Bach announced today. Back to TopSource: Select
Committee on Defence, Session 2001-2002, Fourth
Report - Major Procurement Projects Memorandum from the Ministry of Defence on Major Procurement Project Survey (March 2002) [Note that this memo supersedes an earlier memo] FUTURE CARRIERS- (CVF) The decision in the Strategic Defence Review to purchase two large aircraft carriers to replace the three Invincible-class carriers from around 2012 is being taken forward and competitive contracts for the CVF Assessment Phase were awarded in November 1999 to BAe Land and Sea Systems (now BAE SYSTEMS) and Thomson-CSF (now Thales Naval Ltd). The first part of this phase examined a wide range of carrier designs, to reflect the options for the Future Joint Combat Aircraft (JCA (formerly known as the Future Carrier Borne Aircraft (FCBA))—see separate memorandum). This work helped to inform a decision, in January 2001, to select the Joint Strike Fighter (JSF) as the aircraft with the best potential to meet the JCA requirement. A new strategy for the remainder of the Assessment phase was agreed in Autumn 2001 and a revised Stage 2 of Assessment began in November 2001. Carrier design work is now focusing on vessels capable of supporting JSF pending a decision on aircraft variant selection, which is currently planned by autumn 2002. OPERATIONAL REQUIREMENT 1. The Strategic Defence Review (SDR) concluded that the ability to deploy offensive air power will be central to future force projection operations, and that aircraft carriers can provide valuable flexibility in a range of operational circumstances. They can also offer a coercive presence, which may forestall the need for war fighting. The SDR recognised that there is an increasing likelihood of future operations being conducted by forces far from their home bases. In such operations, host-nation support, including access to suitable air bases, cannot be guaranteed, particularly during an evolving regional crisis or the early stages of a conflict. The SDR concluded that there is a continuing need for Britain to have the capability offered by aircraft carriers. Our three Invincible-class carriers were designed for Cold War anti-submarine operations. Our intention, announced in the SDR, is to replace these with a new class of larger and more capable carriers, known as the Carrier Vessel Future (CVF) class. 2. In accordance with the Smart Acquisition model, CVF is following a two-stage approval process that involves an Initial and a Main Gate. Initial Gate approval, utilising the Smart Acquisition model, was given in December 1998 for an Assessment phase. Studies being undertaken in Assessment with examine the User Requirement Document and develop it, using cost/capability trade-offs to produce an affordable and achievable System Requirements Document. The objective is to build a replacement for the current carriers that has an increased emphasis on offensive air operations and is capable of operating the largest possible range of aircraft in the widest possible range of roles. TRADE-OFFS 3. Trade-offs between cost and capability and time and capability are integral to the Assessment Phase work. NUMBERS 4. The original plan was to replace the three Invincible-class carriers with three 20,000 tonne vessels. Operational analysis demonstrated, however, that it would be more cost-effective to procure two large carriers, each capable of carrying up to about 50 aircraft. The SDR also saw advantage in future carriers being capable of carrying more fixed-wing aircraft than the current vessels, in order to be able to contribute more effectively to the support of operations on land and at sea. STRATEGIC DEFENCE REVIEW 5. The SDR assessed the requirement for aircraft carriers within the overall requirement for an offensive air capability. It concluded that "there is....a continuing need for Britain to have the capability offered by aircraft carriers" and the emphasis for replacement carriers should be on "increased offensive air power, and an ability to operate the largest possible range of aircraft in the widest possible range of roles" (The Strategic Defence Review, Supporting Essays, pages 6-6 to 6-8). MILITARY CAPABILITY 6. The CVF will deploy offensive air power in support of the full spectrum of future operations, including force projection, as a central component of the maritime contribution to joint operations. EQUIPMENT TO BE REPLACED AND IN -SERVICE DATE 7. The planned out of service dates for HMS Invincible, HMS Illustrious, and HMS Ark Royal are 2010, 2012 and 2015 respectively. The SDR introduced no changes to this programme of withdrawals from service. The first CVF is scheduled to enter operational service in 2012 and the second in 2015. The in-service date of CVF will be declared as the date when the military capability provided by the CVF is assessed as available for operational use in its minimum usefully deployable form, i.e at least as capable as the system it replaces. ACQUISITION APPROACH 8. The CVF procurement strategy is based on competition and prime contractorship, with clear and unambiguous output requirement specifications. 9. Invitations to tender for the Assessment Phase were issued in January 1999 to six potential prime contractors—BAE, Lockheed Martin, Boeing, Marconi Electronic Systems, Raytheon, and Thomson-CSF. Responses were received in May from two teams: the .rst led by Thomson-CSF of France with BMT Defence Services Ltd and Raytheon Systems as major sub-contractors; the other by BAe Land and Sea Systems with Marconi Electronics Systems as a sub-contractor. Following tender evaluation and face-to-face meetings with industry it was judged that the bids offered the basis for robust and e.ective competition and contracts were awarded to both teams in November 1999. BAe and Marconi subsequently merged to form BAE SYSTEMS and in February 2000 Lockheed Martin joined the Thomson-CSF team (now known as Thales). 10. The Assessment phase was originally intended to comprise two main stages. The first involved the examination of carrier design options and helped inform the decision, in January 2001, to select JSF as the aircraft with the best potential to meet the FJCA requirement. Reflecting this decision, the remainder of Stage 1 focused on vessels capable of supporting JSF. 11. Stage 2 was previously planned to involve detailed work, informed by our choice of JSF, to determine the carriers’ design parameters and to reduce technological risk, and culminate in the Main Gate approval decision, planned for December 2003, to down-select to one preferred prime contractor to proceed to Demonstration and Manufacture. 12. The first stage of Assessment was completed in June 2001. The Department carefully considered the proposals received from the contractors for the originally configured Stage 2, taking into account their views of the amount of work required to minimise the level of risk in the CVF programme. Having revisited our strategy to determine the most efficient and cost effective way forward for the remainder of the Assessment Phase, we concluded that the original approach no longer offered best value for money. 13. As a result, the CVF procurement strategy was changed. In a revised and shortened stage 2, until November 2002, the competing consortia will concentrate on refining their designs and on taking key tradeoff decisions. During this period the Department will continuously assess the two consortia’s work so that we can announce a single preferred prime contractor in early 2003. 14. The selected prime will then work on the third stage of assessment from early 2003 through to the award of a Demonstration and Manufacture contract early in 2004. 15. In adopting this revised approach we are seeking to apply Smart Acquisition principles. This approach will allow us to maximise the advantages offered by competition and thus ensure that we achieve best value for money. The new strategy concentrates the forces of competition at appropriate levels; namely between the candidate primes whilst designs are refined and key trade-off decisions are made; and then, once the prime has been selected, at the sub-contractor level to ensure that robust prices are achieved. The new strategy will allow a seamless transition from Assessment through to Demonstration and Manufacture. The strategy also addresses industry’s concerns about the level of risk reduction required on major programmes. Both BAE SYSTEMS and Thales have welcomed the revised approach. 16. The revised strategy provides additional funding for the remainder of the Assessment Phase but offsets this by the fact that only one prime will be contracted for Stage 3 post-November 2002. We will also seek to withhold some of the payments for this stage until after the award of the D&M contract. The additional cost of the revised strategy is around £20 million. This additional funding will enable the selected prime to compile more confidently their performance, time and cost proposals, which we will expect them to achieve during the build programme. The programme remains within its previously approved maximum acceptable cost for the Assessment phase. The planned In-Service Dates of the two carriers remain unchanged at 2012 and 2015. 17. The Demonstration element of the D&M phase will initially continue design and risk reduction work from the Assessment Phase, the intention being to achieve the highest possible level of mature design before construction begins. 18. A cost model has been developed to generate whole-life cost estimates for CVF and this is populated with regularly updated data from industry. In the event of competition collapsing before the end of Stage 2, this model would be used as the basis for negotiations with industry. ALTERNATIVE ACQUISITION OPTIONS 19. During the first stage of Assessment, a wide range of carrier and aircraft options, including conventional take-o. and landing, short take o. and vertical landing, and short take off but arrested recovery were considered. As part of this work and following normal practice, the cost of extending the three existing carriers, by ten years, has been assessed to provide a baseline against which the cost effectiveness of all the options can be evaluated. COLLABORATION 20. Whole ship collaboration is unlikely to be a viable option, but opportunities are being reviewed during Assessment, especially for equipment systems and subsystems. In particular, discussions are continuing with the French and US to explore areas for possible co-operation in common areas of aircraft carrier technology at a system or sub-system level. EXPORT POTENTIAL 21. It is unlikely that this project will lead directly to whole-ship sales, although the commercial marketing of CVF design skills and production technology could benefit UK industry. Much of the ship’s equipment could have export potential. Industrial Participation proposals will be invited, as appropriate, for offshore content of the proposed solution. INDUSTRIAL FACTORS 22. In accordance with government policy for the construction of warships, the CVF will be built in a UK shipyard or shipyards. Industrial factors will be taken into account in the selection of the prime contractor. SMART ACQUISITION 23. The CVF programme is adopting and further developing a range of Smart Acquisition techniques including a greater emphasis on identifying, evaluating, and implementing effective trade-offs between system performance, whole-life costs and time; the adoption of incremental acquisition for areas such as the combat systems; and the use of off-the-shelf equipment and commercial standards, where appropriate. An Integrated Project Team (IPT) is managing the project under the leadership of an industrialist recruited in an open competition. In accordance with Smart Acquisition, what would previously have been Feasibility and Project Definition stages have been combined into a single Assessment phase, with increased investment at this stage to achieve early risk reduction. The two consortia have been encouraged to be innovative throughout the project. 24. The preferred contractor for the CVF programme will be selected through a continuous assessment process. This offers a new and faster means of discriminating between two competing contractors. The process also breaks new ground by addressing significant but less tangible ‘soft issues’—such as the contractors’ ability to work with the MoD, which is an important issue when the MoD could be working with the selected prime for many years. The continuous assessment process will run throughout the coming year and will provide the MoD with a robust and fair method of determining which contractor is best placed to build the carriers. It is a move away from the traditional tender assessment approach and should mean that the MoD will be able to make its decision more quickly than would otherwise be possible. ACQUISITION PHASES 25. A number of small-scale pre-feasibility studies were completed prior to the award of the assessment contracts. A risk register will be maintained throughout the life of the project as the core of an integrated risk management system. This contains both MoD and contractor inputs and is the focus for risk reduction work during the Assessment phase. The risk reduction work will help to provide confidence in the data to be assessed in the Combined Operational Effectiveness and Investment Appraisal that will support the Main Gate submission to proceed with Demonstration and Manufacture. MILSESTONES AND COSTS 26. CVF milestones, as currently planned, are shown in the table below.
27. We envisage a total acquisition cost for the two carriers of £3 billion (resource costs, outturn prices), including combat system and initial support costs, but excluding the aircraft. The peak years of expenditure are likely to be between 2008 and 2012. Costs incurred so far, including pre-feasibility studies, total around £46 million. IN -SERVICE SUPPORT 28. We plan to investigate the let of a design/build/through-life support/disposal contract as one package. Collaborative support arrangements are unlikely. 29. Manning levels will be based on work by human factors designers, to achieve a balance between automated and manual tasks, and by training needs analysis, in accordance with the RN training equipment strategy. The size of ship’s complement is planned to be about the same as for the Invincible class. Contractors will be tasked to propose the most efficient manning strategies for their designs, which will be examined during Assessment. 30. All logistic support associated with CVF will be considered as a direct cost to the project, with an emphasis on avoiding expenditure on new infrastructure. The maintenance management system will be required to integrate with other MoD logistic systems and to take account of emerging developments in IT. Innovative support solutions will be examined, using Integrated Logistic Support methodology to minimise costs throughout the ship’s life. 31. Contractor Logistic Support (CLS) will be examined for some or all of the maintenance and logistics. The benefits of CLS include a strong focus on reliability for initial designs; better standards of availability, reliability and maintenance; and an incentive to the contractor to design and build systems that minimise support costs. One option to be considered is the adoption of best practice in supply chain techniques, to minimise MoD ownership of spares, by contracting for agreed spares availability from industry. CLS options for up to 30 years will be examined during Assessment. 32. The upkeep cycle of the CVF will reflect the vessels’ modern design and developments in upkeep practice such as ‘reliability centred maintenance’ rather than lengthy and expensive refits. This will enable availability requirements to be met by only two carriers. FRONT LINE NUMBERS 33. Both CVF will be assigned to the front line. INTEROPERABILITY 34. The aim is to maximise the interoperability of the CVF with the greatest possible range of UK and allied aircraft and with other carriers, to the extent that this can be achieved cost-effectively. This is being explored further during the Assessment phase. DISPOSAL OF EQUIPMENT REPLACED 35. Prospects for the sale of the Invincible class will be explored in due course. IN-SERVICE LIFE 36. Each CVF is planned to have an in-service life of 30 years with a stretch target of up to 50 years. DEVELOPMENT POTENTIAL 37. The CVF programme is closely linked with JCA and Maritime Airborne Surveillance and Control (MASC—formerly known as the Future Organic Airborne Early Warning (FOAEW) programmes (the latter managed by a dedicated team within the CVF Integrated Project Team). Back to Top
|
| User Requirements Document endorsement and Initial Gate approval | December 1998 |
| Issue ITT | January 1999 |
| Start ITT Assessment | November 1999 |
| FCBA variant selection | 2001-02 |
| FCBA decision | January 2001 |
| Systems Requirement Document endorsement and Main Gate approval | December 2003 |
| Order date | 2004 |
| ISDs | 2012 and 2015 |
19. We envisage a total acquisition cost for
the two carriers of £2.7 billion at outturn prices (EP 2001), including
combat system and initial support costs, but excluding the aircraft. The
peak years of expenditure are likely to be between 2008 and 2012. Costs
incurred so far, including pre-feasibility studies, total just over £16
million.
IN -SERVICE SUPPORT
20. We plan to investigate the let of a
design/build/through-life support/disposal contract as one package.
Collaborative support arrangements are unlikely.
21. Manning levels will be based on work by
human factors designers, to achieve a balance between automated and
manual tasks, and by training needs analysis, in accordance with the RN
training equipment strategy. The size of ship's complement is planned to
be about the same as for the Invincible class. Contractors will be
tasked to propose the most efficient manning strategies for their
designs, which will be examined during Assessment.
22. All logistic support associated with CVF
will be considered as a direct cost to the project, with an emphasis on
avoiding expenditure on new infrastructure. The maintenance management
system will be required to integrate with other MoD logistic systems and
to take account of emerging developments in IT. Innovative support
solutions will be examined, using Integrated Logistic Support
methodology to minimise costs throughout the ship's life.
23. Contractor Logistic Support (CLS) will be
examined for some or all of the maintenance and logistics. The benefits
of CLS include a strong focus on reliability for initial designs; better
standards of availability, reliability, and maintenance; and an
incentive to the contractor to design and build systems that minimise
support costs. One option to be considered is the adoption of best
practice in supply chain techniques, to minimise MoD ownership of
spares, by contracting for agreed spares availability from industry. CLS
options for up to 30 years will be examined during Assessment.
24. The upkeep cycle of the CVF will reflect
the vessels' modern design, and developments in upkeep practice such as
"reliability centred maintenance" rather than lengthy and
expensive refits. This will enable availability requirements to be met
by only two carriers.
FRONT LINE NUMBERS
25. Both CVF will be assigned to the front
line.
INTEROPERABILITY
26. The aim is to maximise the
interoperability of the CVF with the greatest possible range of UK and
allied aircraft and with other carriers, to the extent that this can be
achieved cost-effectively. This is being explored further during the
Assessment phase.
DISPOSAL OF EQUIPMENT REPLACED
27. Prospects for the sale of the Invincible
class will be explored in due course.
IN -SERVICE LIFE
28. Each CVF is planned to have an in-service
life of 30 years.
DEVELOPMENT POTENTIAL
29. The CVF programme is closely linked with the FCBA and Future Organic Airborne Early Warning programmes (the latter managed by the CVF Integrated Project Team).
Source:
Ministry of Defence - Fact
Sheet
Date: January 2001
FUTURE
AIRCRAFT CARRIER (CVF) - FACT SHEET
- Future Carrier Borne Aircraft (FCBA) – Joint Strike Fighter
- Future Organic Airborne Early Warning (FOAEW)
- Helicopters in a variety of roles that could include anti-submarine warfare, support and attack
- EH101 (Merlin) helicopter
- V-22 Osprey tilt-rotor
- E-2C Hawkeye
- Unmanned Aerial Vehicles(UAVs)/ Lighter Than Air Vehicles (LTAVs)
Source: Select
Committee on Defence, Session 1999-2000, Written
Evidence
Date: 28 June 2000
Further Memorandum from the Ministry of Defence (19 April 2000)
[Note that this memo superceeds an earlier memo]
FUTURE CARRIERS—CVF
The decision in the Strategic
Defence Review to purchase two large aircraft carriers, to replace the
three Invincible-class carriers from around 2012, is being taken forward
and competitive contracts for the CVF Assessment Phase were awarded in
November 1999 to BAe Land and Sea Systems, now BAE Systems, and Thomson-CSF.
The first part of this phase, Analysis of Options, is examining a wide
range of carrier design options, to reflect the options for the Future
Carrier Borne Aircraft, FCBA, see separate memorandum.
OPERATIONAL REQUIREMENT
1. The
Strategic Defence Review concluded that the ability to deploy offensive
air power will be central to future force projection operations, and
that aircraft carriers can provide valuable flexibility in a range of
operational circumstances. They can also offer a coercive presence,
which may forestall the need for war fighting. The SDR recognised that
there is an increasing likelihood of future operations being conducted
by forces far from their home bases. In such operations, host-nation
support, including access to suitable air bases, cannot be guaranteed,
particularly during an evolving regional crisis or the early stages of a
conflict. The SDR concluded that there is a continuing need for Britain
to have the capability offered by aircraft carriers. Our three
Invincible-class carriers were designed for Cold War anti-submarine
operations. The intention, announced in the SDR, is to plan to replace
these with a new class of larger and more capable carriers, known as the
CVF, Carrier Vessel Future, class.
2. In
accordance with the Smart Procurement model, CVF is following a
two-stage approval process that involves an Initial and Main Gate.
Initial Gate approval, utilising the Smart Procurement model, was given
in December 1998 for an Assessment phase. Studies being undertaken in
Assessment will examine the User Requirement Document and develop it,
using cost/capability trade-offs to produce an affordable and achievable
Systems Requirements Document. The objective is to build a replacement
for the current carriers that has an increased emphasis on offensive air
operations and is capable of operating the largest possible range of
aircraft in the widest possible range of roles.
TRADE-OFFS
3. Trade-offs
between cost/capability and time/capability are integral to the
Assessment work.
NUMBERS
4. The
original plan was to replace the three Invincible-class carriers with
three 20,000 tonne vessels. Operational analysis demonstrated, however,
that it would be more cost-effective to procure two large carriers, each
capable of carrying up to about 50 aircraft. The SDR also saw advantage
in future carriers being capable of carrying more fixed-wing aircraft
than the current vessels, in order to be able to contribute more
effectively to the support of operations on land and at sea.
STRATEGIC DEFENCE REVIEW
5. The
SDR assessed the requirement for aircraft carriers within the overall
requirement for an offensive air capability. It concluded that
"there is ... a continuing need for Britain to have the capability
offered by aircraft carriers" and the emphasis for replacement
carriers should be on "increased offensive air power, and an
ability to operate the largest possible range of aircraft in the widest
possible range of roles"—The Strategic Defence Review, Supporting
Essays, pages 6-6 to 6-8.
MILITARY CAPABILITY
6. The
CVF will deploy offensive air power in support of the full spectrum of
future operations, including force projection as a central component of
the maritime contribution to joint operations.
EQUIPMENT TO BE REPLACED AND IN -SERVICE DATE
7. The
planned out of services dates for HMS Invincible Illustrious and HMS Ark
Royal are 2010, 2012 and 2015 respectively. The SDR introduced no
changes to this programme of withdrawals from service. The first CVF is
scheduled to enter operational service in 2012 and the second in 2015.
The in-service date for CVF is defined as the "Operational Date
Materiel Assessment", which is the date at which it will be
accepted as fit for entry into the operational fleet.
PROCUREMENT APPROACH
8. The
CVF procurement strategy is based on competition and prime
contractorship, with clear and unambiguous output requirement
specifications. Although we intend that the ships should be built in the
UK, prospective prime contractors are from the UK and France.
9. In
accordance with the Smart Procurement model, the project is following a
two-stage approval process. Invitations to tender for the Assessment
phase were issued in January 1999 to six potential prime contractors—BAe
Lockheed Martin, Boeing, Marconi Electronic Systems, Raytheon, and
Thomson-CSF. Responses were received in May from two teams; the first
led by Thomson-CSF of France with BMT Defence Services Ltd and Raytheon
systems as major sub-contractors; the other by BAe Land and Sea Systems
with Marconi Electronics Systems as a sub-contractors. Following tender
evaluation and face-to-face meetings with industry it was judged that
the bids offered the basis for robust and effective competition and
contracts were awarded to both teams in November 1999. BAe and Marconi
subsequently merged to form BAE Systems, and in February 2000 Lockheed
Martin joined the Thomson-CSF team.
10. The
Assessment phase comprises two main stages. The first, analysis of
Options, involves the examination of carrier design options and will
help inform the decision, expected in late 2000/early 2001, on the type
of aircraft to meet the Future Carrier Borne Aircraft, FCBA,
requirement. Progress to the second stage of Assessment will be subject
to satisfactory completion by BAE Systems and Thomson-CSF of stage one,
based on a review of their performance, and the timeliness and quality
of their deliverables. The second stage will involve detailed work to
determine the carriers' design parameters and to reduce technological
risk, informed by the choice of FCBA. It will culminate in the Main Gate
approval decision, planned for 2003, to down-select to one preferred
prime contractor to proceed to Demonstration and Manufacture of two
carriers. The Demonstration phase will begin with the design of a
virtual prototype by the selected prime contractor, using computer-aided
technology. The intention is to achieve, so far as possible, a freeze on
a mature design before construction begins.
11. A
cost model is being developed to generate whole-life cost estimates for
CVF and this will be populated with data from industry. In the event of
competition collapsing, this model would be used as the basis for No
Acceptable Price, No Contract negotiations.
ALTERNATIVE PROCUREMENT OPTIONS
12. During
Assessment, a wide range of carrier and aircraft options, including
conventional take-off and landing, short take off and vertical landing,
and short take off but arrested recovery will be considered. As part of
this work and following normal practice, the cost of life-extending the
three existing carriers, by10 years, will be assessed to provide a
baseline against which all the options can be evaluated.
COLLABORATION
13. It
is too early to be specific about the prospects for collaboration. Some
informal discussions have taken place with the US, Spanish, French, and
Italian navies to identify any common ground in carrier replacement
programmes or requirements. At present, whole ship collaboration would
appear unlikely to be a viable option, but collaborative opportunities
will be reviewed during Assessment, especially for equipment and
systems.
EXPORT POTENTIAL
14. It