![]() |
![]() |
![]() |
|
|
RN Year in Review - 2004 Slightly ahead of time, but perhaps better than my typical February dateline! This is the fifth time that I’ve written a “RN Year in Review” and sadly each time I've had to say that it was overall a bad year for the Royal Navy, at least in the project orientated context that this site focuses on. For example, a year ago I said “2003 proved to be another year of ups and downs for the Royal Navy. Firstly, the Iraq War, secondly the new aircraft carrier (CVF) saga, thirdly delays to urgently needed new construction, and fourthly the spectre of big defence cuts and disposals.” This year has proved to more of same, only the downs have been much lower and the ups would be scarcely noticeable even on a billiard table.
Other non-events then followed; the Future Surface Combatant (FSC) Main Gate was delayed yet again, this time to early 2005. The Initial Gate for the Maritime Airborne Surveillance and Control (MASC) project was missed, as was that for the Military Afloat Reach and Sustainability (MARS) – indeed we are still waiting for public domain news of the revised dates. The Surface Combatant Maritime Rotorcraft (SCMR) also missed its Main Gate, and - as usual - did the Joint Casualty Treatment Ship (JCTS). Also on 31 March 2004 the withdrawal from service of the Sea Harrier FA.2 began when 800 squadron was disbanded. This process will be completed in March 2006 – leaving the RN with no carrier based air defence capability until the F-35B Joint Strike Fighter (JSF) enters service. Unfortunately, just as the run down of the RN's Sea Harrier force began in earnest, it was announced across the Atlantic that the F-35B JSF would be delayed by two years. All being well, the UK can probably hope to have a grand total of 8 F-35B’s cleared for operational service by the end of 2014. The only slight mitigating circumstance is that probably the first CVF carrier won't be in service before that date anyway! But the expected delays to CVF and the JSF have not stopped the MOD from advancing the decommissioning of the last Invincible-class carrier (HMS Ark Royal) from 2015 to 2013.
Amazingly, since July things have continued
to get worse as more bad news has emerged. The delay to
the SCMR Initial Gate began to make sense as rumours started to
circulate
that the billion pound cut in helicopter procurements which was
indirectly announced in the White
Paper would be mostly found by cancelling SCMR outright, leaving
the RN with only its small force (currently 42 airframes) of
EH-101 Merlin helicopters by about 2014. Also, funding for MASC
has faded away; instead the project appears to have become the
Maritime Strand of the Joint UAV Experimentation Programme (JUEP).
But most disappointing of all, in November perhaps the most exciting RN
design concept since HMS Dreadnought a century ago was
cancelled.
Other project news during the year … the in-service date for the first Bay-class LSD(A) was delayed by about 18 months to late 2005, and the in-service date for the first Type 45 HMS Daring was also delayed by 18 months to May 2009. The extra cost of running on the ancient Type 42 destroyers will be met by reducing the equipment fit of the Type 45’s – effectively by elimination of the planned Incremental Acquisition Plan. Another development is that long time pleas by UK naval shipbuilders for the MOD to adopt a more considered approach to naval orders in order to avoid the “famine to feast to famine” cycle has finally had some reaction. In late 2003 the MOD commissioned a report from RAND Corp to evaluate the UK situation, and a DPA team began to develop a new naval shipbuilding strategy. Their findings are now being developed in to a programme by the Maritime Coherence Study, which in turn will be used to inform the MOD’s Equipment Plan – how’s that for rapid response! The general conclusion seems to be that the shipbuilding industry will indeed have trouble coping with MOD future orders, but rather than advance orders to alleviate the current “famine” as industry hoped, the problem seems to have already become an excuse for the MOD to actually delay orders and projects in order to reduce the forecast "feast"!
The only naval order almost awarded by the MOD during 2004 (on 13 December VT Group announced that had entered contract negotiations) was for a single new OPV(H) to replace the two existing Castle-class, i.e. the Royal Navy entire “New Construction Programme” for 2004 was one patrol vessels of under 2000 tonnes - as recently as the late 1970’s three frigates/destroyers and a nuclear submarine was the minimum ever seen. The intensive politics and lobbying that surrounded this order, which is worth about one half of a Eurofighter Typhoon fighter, is perhaps a sign of just how little work UK shipyards have to fight over, despite the governments claim to have the largest naval shipbuilding programme since WW2. Good news is hard to come by, but the overstretched Royal Navy has as ever performed sterling service around the world, and been a credit to the United Kingdom. The Royal Marines perhaps deserve a particular mention, they have fought off attempts by the Army to take control of it, apparently the new Commando 21 organisation is proving to be a success, and the hard worked 3 Commando Brigade is deservedly recognised as a big reason why the UK can still “punch above its weight” militarily. The UK's amphibious force has been greatly enhanced by the arrival in service at last of the Albion-class LPD/Command ships, and perhaps 2005 will see the RM’s finally get to order the new hovercraft that they badly want. Also, thankfully the Astute SSN project seems to be on the road to recovery, the first unit is still expected to enter service in 2009, just four years later than were being told in 2002. The coming year will see the bicentennial of the Battle of Trafalgar. Let's hope Nelson won’t be turning in his grave on come the 21st of October (or the International Fleet Review in June), and I personally hope a year from now to be able to write a far more positive editorial.
|
|
© 2004-8 Richard Beedall unless otherwise indicated. |